Migrating to Sybase Adaptive Server Enterprise 11.5 D-11
Adaptive Server Enterprise 11.5 Parallel Migration Task List Example
5. Verify and document SQL Server 10.x regression test.
6. Verify performance and functions on Server B’s SQL Server 10.x.
Upgrade SQL Server on Server B (Shadow)
1. Alter sybsystemprocs.
2. Perform pre-upgrade verification.
3. Upgrade Server B to Adaptive Server 11.5.
4. Load Adaptive Server 11.5 environment from media dumps.
5. Run
dbcc commands (checktable, checkalloc, checkcatalog).
6. Set baseline Adaptive Server 11.5 configuration parameter
values.
7. Perform Release 10.x dump from Server A.
8. Load Adaptive Server 11.5 with the Release 10.x dump.
9. Run
dbcc commands (checktable, checkalloc, checkcatalog) on Adaptive
Server 11.5 databases. Be sure to verify the
dbcc log and error log.
10. Recycle Adaptive Server.
Run Post-upgrade Regression Test Suites on Server B
Back-end regression test suite—production loads
1. Perform the back-end regression testing.
2. Monitor and capture system dynamics (
sp_who, sp_lock, statistics io...).
3. Verify and document this SQL Server 10.x regression test.
Front-end simulation regression test suite
1. Perform front-end simulation regression testing.
2. Monitor and capture system dynamics (
sp_who, sp_lock...).
3. Verify and document this SQL Server 10.x regression test.
4. Load Adaptive Server 11.5 from media dump.